Creation of Gati Shakti Directorate- Composition, Functions, Delegation of Power etc.
भारत सरकार Government of India
रेल मंत्रालय Ministry of Railways
रेलवे बोर्ड (Railway Board)
Office Order No. 37 of 2022
Sub: Creation of Gati Shakti Directorate- Composition, Functions, Delegation of power etc.
It has been decided to create a new Directorate namely ‘Gati Shakti Directorate’ by clubbing Plan Heads (PH)- 11, 14, 15, 16, 33, 35 & 81 presently dealt with by Works, Signal, RE Directorate into one Directorate as named above to bring synergy and to improve efficiency of the system so as to create additional rail infrastructure and thereby enhance railway market share in country’s cargo loading and reduce logistic cost.
2. The new Gati Shakti Directorate would be headed by AM/PED designated as AMJPED(GS). The composition and brief duty list of the Gati Shakti Directorate is enclosed at Annexure-1.
2.1 Gati Shakti Directorate will work with the existing strength of Works, RE and Signal Directorate and of Project Branch included in Gati Shakti Directorate. Further strengthening of Gati Shakti Directorate would be undertaken in due course as per need.
2.2 As regards, Financial Powers it would be in line with the extant instructions issued vide Office Order No. 01 of 2017 and the same procedure as enclosed at Annexure-II would be followed for Appraisal and Approval of Public Funded Umbrella Projects dealt with by Gati Shakti Directorate.
3. All proposals emanating from Gati Shakti Directorate will be concurred by its own Associate Finance. For technical approval of the project under PH-33 & 35, the proposal will be routed through concerned AMs.
3.1 The Survey proposals/DPRs/Survey Reports after examination and concurrence of associate finance will be put up to Board through Board memorandum/Note and same will be presented to the Board, if required. The Board may approve or modify as the case may be. Thereafter, proposal, if required, will be processed to Hon’ble MR. as per the extant provisions.
4. The newly created Gati Shakti Directorate will report to Member Infrastructure, Railway Board. However, APAR of concerned EDs will be initiated by AM/PED (Gati Shakti), reviewed by concerned Board Member and accepted by CRB & CEO. Additional Member/RE will continue to report to Member Infrastructure regarding all policy matter and technical approvals of RE projects. ED/Electrical will report to AM/RE on these matters.
5. For implementation purpose, all the officers working in Gati Shakti Dte. will also work concurrently in their existing Directorate for other works listed in their subject list till the new system stabilize. The existing Directorate will mainly be involved in policy formulation in their subject matter, sanction and monitoring of works other than Gati Shakti works, Parliament related works, RTI etc.
6. The above issues with the approval of Minister of Railways.
No.2022/0&M/6/1
Dated: 26/05/2022
(B. Majumdar)
Joint Secretary/Railway Board
Signed copy download PDF